Fire Pump & Tank Sizing Lab

Combine the sprinkler and wet riser demands, pick a listed fire pump size to NFPA 20, set the jockey and pump start pressures, size the motor or diesel engine and the electrical supply, then size the fire water tank. Watch the start sequence play out on a pressure trace.

NFPA 20NFPA 14NFPA 13UAE Fire & Life Safety CodeBS EN 12845AS 2941

How to use: start with the defaults or press Import from FF-202 to bring in your sprinkler result. Tap i next to any field for a plain explanation.

1. Demands and supply

The pump must meet the largest of the system demands.

Sprinkler system
Wet riser / standpipe
Suction and pump
Fire water tank

2. Pump room

Duty, standby and jockey pumps with headers, test line and tank. Press play to run the start sequence.

3. Checks

    4. Pump curve against demands

    Listed pump curve through churn, rated and 150% flow at 65% of rated pressure.

    5. Selection summary

    6. How the selection works

    Which demand governs

    The sprinkler demand comes from the hydraulic calculation, plus hose allowance. The wet riser demand to NFPA 14 is 1,893 L/min for the first Class I or III riser and 946 L/min for each extra riser, capped at 3,785 L/min in a sprinklered building, with 6.9 bar at the top outlet. In a combined system the larger demand usually governs.

    Choosing the pump

    NFPA 20 pumps come in listed ratings. The lab picks the smallest rating that covers the demand flow, then sets the rated pressure from the required pressure minus the suction pressure. A listed pump must give at least 65% of rated pressure at 150% of rated flow and its churn may not exceed 140%.

    Pressure settings

    The jockey pump stops at churn plus static suction and starts 0.7 bar lower. The duty fire pump starts 0.35 bar below the jockey start, and each further pump 0.7 bar lower again, so the pumps never fight each other.

    Driver and power

    Shaft power is flow × pressure / (600 × efficiency) in kW with L/min and bar. The motor must not overload anywhere on the curve, so it is checked at 150% flow. Diesel engines lose about 1% for every 5.6 °C above 25 °C, which matters in Gulf pump rooms.

    Tank

    Effective volume is the total demand × duration. Add the volume below the suction or vortex plate that the pump can never draw. Two compartments let one half be cleaned while the other stays in service.

    Learning and checking tool. Final pump selection must use the listed pump curve, the authority's approval and the project fire strategy.

    Quick summary in your language

    Read this lab's key points in English, Urdu, Hindi or Arabic. The lab itself is in English.

    This lab sizes the fire pump and water tank from the sprinkler and wet riser demand, with jockey pump settings and starting power. Test the pump at churn, rated and peak flow at commissioning.

    About this lab: Fire Pump & Tank Sizing Lab

    Fire Pump & Tank Sizing Lab

    Size a fire pump and tank: sprinkler and wet riser demands, listed NFPA 20 pump curve, jockey and start pressures, motor, diesel derating, starting kVA and tank volume.

    Topics you can explore

    • Combining sprinkler and wet riser demands
    • Listed pump ratings and the 150% point
    • Churn pressure and component ratings
    • Jockey and fire pump set points
    • Motor sizing, feeder and starting kVA
    • Diesel heat derating
    • Tank volume and compartments

    Practical engineering example

    A tower with two Class I wet risers needs 2,839 L/min at about 12 bar, while the sprinklers need 2,046 L/min at 4.3 bar. The risers govern, so the lab selects a 2,839 L/min (750 gpm) pump and warns that churn may exceed 12.1 bar at the lower landing valves.

    Developed by Eng. Mannan Maqsood. Verify against current project requirements and the applicable authority rules.

    Project checks

    Compare the fire-pump duty and driver with the approved hydraulic demand, available water and applicable duration. Verify the electrical or fuel supply and testing arrangements separately from the tank calculation.

    NEXT STEP

    Where to go from here

    Related labs that pick up where this one ends.

    Sprinkler Hydraulic CalculatorWork out the sprinkler demand first.FF-202 →Standby Generators & Emergency PowerSize the generator for the fire pump start.E-112 →Fire Alarm System Virtual LabPump running and fault signals to the panel.FA-201 →Clash Detection LabRoute fire mains around other services.E-121 →
    Your work in each lab is saved in this browser.Save or move my progress · All 127 labs · Ask the Copilot