LV switchgear FAT: what to check before the panel leaves the factory

By Eng. Mannan Maqsood, Electrical EngineerPublished 4 min read

A defect found at the factory costs a few hours of a panel builder's time. The same defect found after the board is installed, cabled and energised can cost weeks: a shutdown, a new part shipped from overseas, and a second witness test. The factory acceptance test (FAT) is the last cheap moment to catch problems. Yet many FATs are rushed, with the visitors looking at the paint and the nameplate and signing a pre-printed form. This article sets out what to check, in an order that works on the day.

Before you travel

1. Compare the board with the drawings

Walk the board section by section with the approved GA and SLD in hand.

Mark every difference on the drawing. Small substitutions, such as a different meter model or an MCCB from another range, need an approved deviation, not a verbal agreement at the FAT.

2. Routine verification to IEC 61439-1

These are the checks the standard requires on every assembly. Witness them, or witness a sample and review the records for the rest.

3. Functional tests

4. Labels, finish and documents

The defects that turn up most often

  1. Trip unit settings left at factory default instead of the coordination study values
  2. Busbar joints without torque marks, or a few bolts clearly loose
  3. Interlock that can be defeated by operating in a different order
  4. Earth straps missing on doors carrying electrical equipment
  5. Cable terminals too small for the cable sizes on the cable schedule
  6. Different meter or relay model from the approved submittal
  7. Form of separation barriers missing in one section
  8. Labels wrong or missing, especially on spare ways

Close it properly

End the FAT with a written snag list that lists each item, the agreed action and who will verify it, and record whether the board is accepted, accepted subject to snags, or rejected. Do not sign "accepted" with open items that affect safety or ratings. The LV Switchgear Verification & Assembly Lab walks through the routine verification and builds a FAT certificate, and the Switchgear & DB Checklist Suite gives printable checklists. The acceptance values for your project always come from the approved specification, the standard and the manufacturer.

About the author: Eng. Mannan Maqsood

Electrical Engineer · Founder of MEPVirtual

Electrical engineer with more than 21 years in the UAE and New Zealand, including senior consulting reviews in Dubai and project electrical engineering on Auckland's City Rail Link. Each article states whether an example comes from a site observation, a technical review or a teaching calculation.

More about the author. MEPVirtual on LinkedIn

Disclaimer. This article is general technical information for education only. It is not professional engineering, design, legal or safety advice for any specific project, and it does not replace the judgement of a qualified, registered engineer who has reviewed the actual installation. Worked examples and figures are illustrative and do not describe any identified project, client or site. Codes, authority requirements and product data change, so confirm every value against the edition that applies to your project, the authority having jurisdiction and the manufacturer's data. Any testing or work on live systems must be carried out only by competent, authorised people under the approved procedure. The views are the author's own and do not represent any employer, client or authority. To the extent permitted by law, the author, the editor and MEPVirtual accept no liability for any loss, damage or injury arising from the use of, or reliance on, this content. See the full disclaimer or report a correction.