M MEPVirtual Design Basis & Authority Lab

Global MEP Virtual Lab

Design Basis & Authority Workflow

Pick a utility, set the building, and watch the load, transformers, substation, fault levels and approval path update live. Concept-stage thumb rules for load requisitions and early coordination.

LV system
Frequency
Utility MV
Cooling factor

How to use: pick the region, building type, area and floors and you have a full design basis. Every other value starts at a typical default you can change. Tap any i for a plain-language explanation, and use Reset to go back to the defaults.

Max demand
Transformers
Isc @ LV terminals
Voltage drop to DB
Life safety genset

Try a Real DEWA-Approved Project

ItemThis lab (live)DEWA approvedDifference

Project names, plots and approval numbers removed. Change any input and the lab column updates, so you can see which assumption moves the result.

Building

Above ground: ground, mezzanine, podium and typical floors.

Calculated: (GFA - car park) ÷ floors. Nothing to enter.

Default for this building type (car parks, plant rooms and shafts are not cooled). Change it if needed.

Hotel Facilities

Lighting

HVAC Cooling Thumb Rule

Whole system: chillers, pumps, towers and air-side fans. COP = 3.517 / (kW/TR).

TR = Conditioned area / (m²/TR) → HVAC kW = TR x kW/TR =

Auxiliary Loads

Vertical transportation matrix

TypeQtyCapacitySpeedkW eachTotal kW

Life safety loads (fire mode)

Usually fed from the essential bus with generator backup and left out of normal MD, since fire mode and full building load do not coincide.

Diversity & Maximum Demand

Typical diversity factors for this building type and a 0.90 power factor are applied. Adjust them below.

GroupConn. kWDFDemand kW
Total (TCL / MD)
MD (kVA) = Σ(kW x DF) / PF =

Demand Load Share

Connected vs Demand

Transformer Allocation

N = ⌈MD x / S⌉
= ⌈⌉ =
Loading-cap check: ⌈MD / (S x )⌉ =
Duty units = ( governs), total =
Duty transformer loading

Single Line Diagram (live)

Energized

Substation Space Sizing

RMU room
LV room (MLVB line-up)
Total substation footprint
Clear height
Cable trench depth
MV current per transformer

Basis: ~42 m² for 2 x 1500 kVA plus ~22 m² per extra unit, scaled for 1000 / 2000 kVA. Final sizes follow the utility standard substation drawings.

Substation Plan (2D, to scale)

Short-Circuit at Transformer

Irated = S / (√3 x V) =
Isc (infinite bus) = Irated / Z =
Isc (with source) = Irated / (Z + S/Ssc) =
ipk = n x Isc = (IEC 60947-2)
Isc rms
Incomer

Voltage Drop Cascade: Transformer to Final DB

ΔV (%) = √3 x I x L x (R cosθ + X sinθ) / VLL x 100, cosθ =

Earth Fault Loop Impedance (Zs) & ADS Check

Ze = Ztx + ZMV =  |  Zs = Ze + Σ(R1 + R2)  |  ADS when Zs ≤ x U0 / Ia, U0 = V
PointProtective deviceEarth pathZsEarth fault IIa to tripMax ZsTimeStatus
Fix options: shorten the circuit, upsize the CPC or the phase conductor, use a lower magnetic setting or Type B MCB, or add RCD / earth fault (G) protection so disconnection no longer depends on overcurrent devices.

TN-S system from the building transformer (Dyn11). Separate Cu CPC sized to BS 7671 Table 54.7, busduct with integral PE bar. Resistances at 90°C operating temperature (conservative). Final circuit 2.5/1.5 mm² with R1+R2 = 19.51 mΩ/m x 1.20. The riser ACB earth fault (G) function and 30 mA RCDs on final circuits give extra margin.

Level 1

Main LV Switchboard (MLVB)

  • sections, Form 4 Type 6, IEC 61439-2
  • Incomer:
  • Bus coupler:
  • Riser feeders:
  • APFC:
  • Plant feeders (HVAC, lifts, pumps):
Level 2

Busbar Risers / SMDBs

  • x (IEC 61439-6)
  • Riser current:
  • Tap-off per floor:
  • Fault level at riser:
  • Floor load total:
  • Neutral:
  • Plant SMDBs: HVAC, lifts, pumps, life safety (essential)
Level 3

Final Distribution Boards

  • DBs ( per floor)
  • Incomer:
  • DB design current:
  • Fault level at DB:
  • Final circuits:

Harmonics & Neutral Sizing Check

Non-linear source (riser fed)Demand kW3rd harm.
Weighted
LocationPhase INeutral ISize cable on
VFD / drive harmonics

Basis: BS 7671 Appendix 4 Table 4Aa / IEC 60364-5-52 Annex E. Neutral current = 3 x third-harmonic current. Six-pulse VFDs mainly produce 5th and 7th harmonics, so they distort voltage but do not add neutral current.

Cascade Schedule

LevelEquipmentQtyProtective deviceDesign IFault levelΣ ΔV
L0RMU T-off (fuse / VCB)0.00%
L1MLVB (IEC 61439-2)
L2
L3Final DB

Approval Path:

Click a step for portals, documents and durations. Press play to run the 4D timeline.

Target energization

Indicative durations using typical ranges and a regional factor. Bars show target calendar dates from the start date above.

Portal / agency (typical)
Submittal checklist

5D CAPEX Estimate

Total electrical distribution CAPEX
Per kVA of MD

Bill of Quantities (auto from the design)

ItemQtyUnitRateAmount
Supply subtotal

Placeholder benchmark rates for concept CAPEX only, not tender prices. Replace them with your own supplier or tender rates below. In some GCC utilities the transformers and RMUs are supplied by the utility against connection charges, so remove those lines if they are not in your scope.

Design Basis Summary

Ready to paste into a load requisition cover note or design basis report.


  

Quick summary in your language

Read this lab's key points in English, Urdu, Hindi or Arabic. The lab itself is in English.

This lab builds a design basis: load estimate, transformer and substation size, voltage drop, fault level and the authority approval route. Start here at concept stage so later design follows the same numbers.

Project checks

Prepare the design basis before filling an authority checklist. Identify which assumptions belong to the utility, the building authority, the project specification and the design team, and record changes where those sources meet.

NEXT STEP

Where to go from here

Related labs that pick up where this one ends, and a learning path to follow.

Cable Sizing, Voltage Drop & Lighting LayoutThe main cable sizing lab: derating, voltage drop, Zs and adiabatic check.Full cable sizing →Standby Generators & Emergency PowerExplore standby generators, load schedules, motor starting, automatic transfer switches.E-112 →DEWA Design Tools & UAE Regs ReferenceExplore UAE electrical design tools for loads, cables, breakers and protection.E-102 →Design Engineering TrackCodes, symbols, loads, cable sizing, drainage and calc sheets in 6 labs.LEARNING PATH →
Your work in each lab is saved in this browser.Save or move my progress · All 127 labs · Ask the Copilot