Global MEP Virtual Lab
Design Basis & Authority Workflow
Pick a utility, set the building, and watch the load, transformers, substation, fault levels and approval path update live. Concept-stage thumb rules for load requisitions and early coordination.
Beginner mode: just pick the region, building type, area and floors. Everything else uses proven defaults. Tap any i for a plain-language explanation.
Expert mode: every engineering assumption is open for editing. Use Reset to go back to the defaults.
Try a Real DEWA-Approved Project
| Item | This lab (live) | DEWA approved | Difference |
|---|---|---|---|
Project names, plots and approval numbers removed. Change any input and the lab column updates, so you can see which assumption moves the result.
Building
Above ground: ground, mezzanine, podium and typical floors.
Calculated: (GFA - car park) ÷ floors. Nothing to enter.
Default for this building type (car parks, plant rooms and shafts are not cooled). Change it in Expert mode if needed.
Hotel Facilities
Lighting
HVAC Cooling Thumb Rule
Whole system: chillers, pumps, towers and air-side fans. COP = 3.517 / (kW/TR).
Auxiliary Loads
Vertical transportation matrix
| Type | Qty | Capacity | Speed | kW each | Total kW |
|---|---|---|---|---|---|
Life safety loads (fire mode)
Usually fed from the essential bus with generator backup and left out of normal MD, since fire mode and full building load do not coincide.
Diversity & Maximum Demand
Typical diversity factors for this building type and a 0.90 power factor are applied. Switch to Expert mode to adjust.
| Group | Conn. kW | DF | Demand kW |
|---|---|---|---|
| Total (TCL / MD) |
Demand Load Share
Connected vs Demand
Transformer Allocation
= ⌈⌉ =
Loading-cap check: ⌈MD / (S x )⌉ =
Connected-load check: ⌈TCL / (S x )⌉ = ⌈⌉ =
Duty units = ( governs), total =
Single Line Diagram (live)
EnergizedSubstation Space Sizing
| RMU room | |
| LV room (MLVB line-up) | |
| Total substation footprint | |
| Clear height | |
| Cable trench depth | |
| MV current per transformer |
Basis: ~42 m² for 2 x 1500 kVA plus ~22 m² per extra unit, scaled for 1000 / 2000 kVA. Final sizes follow the utility standard substation drawings.
Substation Plan (2D, to scale)
Short-Circuit at Transformer
Isc (infinite bus) = Irated / Z =
Isc (with source) = Irated / (Z + S/Ssc) =
ipk = n x Isc = (IEC 60947-2)
Voltage Drop Cascade: Transformer to Final DB
Earth Fault Loop Impedance (Zs) & ADS Check
| Point | Protective device | Earth path | Zs | Earth fault I | Ia to trip | Max Zs | Time | Status |
|---|---|---|---|---|---|---|---|---|
TN-S system from the building transformer (Dyn11). Separate Cu CPC sized to BS 7671 Table 54.7, busduct with integral PE bar. Resistances at 90°C operating temperature (conservative). Final circuit 2.5/1.5 mm² with R1+R2 = 19.51 mΩ/m x 1.20. The riser ACB earth fault (G) function and 30 mA RCDs on final circuits give extra margin.
Main LV Switchboard (MLVB)
- sections, Form 4 Type 6, IEC 61439-2
- Incomer:
- Bus coupler:
- Riser feeders:
- APFC:
- Plant feeders (HVAC, lifts, pumps):
Busbar Risers / SMDBs
- x (IEC 61439-6)
- Riser current:
- Tap-off per floor:
- Fault level at riser:
- Floor load total:
- Neutral:
- Plant SMDBs: HVAC, lifts, pumps, life safety (essential)
Final Distribution Boards
- DBs ( per floor)
- Incomer:
- DB design current:
- Fault level at DB:
- Final circuits:
Harmonics & Neutral Sizing Check
| Non-linear source (riser fed) | Demand kW | 3rd harm. |
|---|---|---|
| Weighted |
| Location | Phase I | Neutral I | Size cable on |
|---|---|---|---|
Basis: BS 7671 Appendix 4 Table 4Aa / IEC 60364-5-52 Annex E. Neutral current = 3 x third-harmonic current. Six-pulse VFDs mainly produce 5th and 7th harmonics, so they distort voltage but do not add neutral current.
Cascade Schedule
| Level | Equipment | Qty | Protective device | Design I | Fault level | Σ ΔV |
|---|---|---|---|---|---|---|
| L0 | RMU T-off (fuse / VCB) | 0.00% | ||||
| L1 | MLVB (IEC 61439-2) | |||||
| L2 | ||||||
| L3 | Final DB |
Approval Path:
Click a step for portals, documents and durations. Press play to run the 4D timeline.
Indicative durations using typical ranges and a regional factor. Bars show target calendar dates from the start date above.
5D CAPEX Estimate
Bill of Quantities (auto from the design)
| Item | Qty | Unit | Rate | Amount |
|---|---|---|---|---|
| Supply subtotal | ||||
Placeholder benchmark rates for concept CAPEX only, not tender prices. Replace them with your own supplier or tender rates in Expert mode. In some GCC utilities the transformers and RMUs are supplied by the utility against connection charges, so remove those lines if they are not in your scope.
Switch to Expert mode to enter your own unit rates.
Design Basis Summary
Ready to paste into a load requisition cover note or design basis report.