HV-511 · HV ACADEMY · FLAGSHIP

HV Testing & Commissioning Lab

Run virtual HV test instruments on cables, transformers, switchgear, CTs and relays. Each test shows what the instrument does, the readings it gives and how to judge them against IEC and IEEE criteria. Simulate healthy and faulty equipment, or type in your own site readings, then print a filled test sheet. Click any for a plain-language explanation.

VLFTan deltaTDRTTRVector groupOil BDVContact resistanceCB timingCT knee pointRelay injection

1. Equipment data

Pick your region first. It loads the utility voltages, typical ratings, ambient, fault level, phase colours and standards. Everything can be changed.

Click any item
Drag to rotate, scroll or pinch to zoom. Running a test in any tab energises the leads and the beacon here.

Engineer's Notes: HV testing and commissioning

Test to prove, not to tick boxes

Commissioning tests prove that equipment arrived undamaged, was installed correctly and is safe to energise. Each result needs a clear acceptance criterion written in the ITP before the test, the instrument serial and calibration date, the temperature, and the names of the tester and witness.

Cables: VLF has replaced DC

For XLPE cables, a VLF withstand at around 3 × U0 for 15 minutes is the usual after-installation test. VLF tan delta adds a health check: low, stable values with little tip-up mean a good cable. A sheath test confirms the outer jacket survived pulling and backfill.

Transformers: ratio, group and resistance

The turns ratio test on every tap, a vector group check, and winding resistance per phase catch most factory, transport and tap-changer faults. Oil breakdown voltage confirms the oil is dry. Compare everything with the factory test report.

Protection: test the whole chain

Secondary injection proves the relay settings and curves. A trip test proves the breaker actually opens. CT polarity, ratio and knee point make sure the relay sees the right current during a fault.

Frequently asked questions

What tests are done on a new 11 kV cable before energising?

Typical after-installation tests are insulation resistance of each core, an outer sheath test, a withstand test (usually VLF at about 3 x U0 for 15 minutes, or as the project and utility specify), and on important circuits VLF tan delta and partial discharge diagnostics. Phasing and screen continuity are also checked.

Why is DC hipot no longer used on XLPE cables?

High-voltage DC testing can leave space charges trapped in XLPE insulation, which can lead to failures after the cable goes back into service, and it is poor at finding defects that matter under AC. VLF (very low frequency, usually 0.1 Hz) AC testing is now the normal choice.

How is VLF tan delta assessed?

IEEE 400.2 uses three numbers for PE and XLPE cables: the stability of tan delta at U0 (standard deviation), the tip-up between 1.5 U0 and 0.5 U0, and the mean tan delta at U0. Each is graded as no action, further study, or action required, and the worst grade decides the condition.

What is the tolerance on a transformer turns ratio test?

IEC 60076-1 allows the lower of plus or minus 0.5 % of the declared ratio, or one tenth of the short-circuit impedance in percent, on the principal tapping. Each tap is checked on every phase.

What is the knee point of a CT?

The knee point is the voltage on the excitation curve where a 10 % increase in voltage causes a 50 % increase in exciting current (IEC 61869-2). Above it the CT saturates, so protection CTs need a knee point comfortably above the voltage needed during a fault.

Topics: ITP · insulation resistance · polarization index · sheath test · VLF withstand · VLF tan delta IEEE 400.2 · TDR · partial discharge · TTR · vector group test · winding resistance · magnetising current · oil BDV IEC 60156 · contact resistance · CB timing · CT knee point · secondary injection · energisation

Related labs

NEXT STEP

Where to go from here

Related labs that pick up where this one ends.

HV Academy hubAll 17 high voltage labs in one learning path.HV ACADEMYGeneration & Renewables Interconnection LabSynchronise a generator on a live synchroscope, check voltage rise and hosting capacity, test loss-of-mains…HV-510 · previousHV Safety & Switching Operations LabPractise HV switching programs, calculate arc flash energy and PPE, see approach boundaries in 3D, follow…HV-512 · nextMV Testing & Commissioning LabVirtual MV commissioning tests: IR and PI, VLF withstand and tan delta to IEEE 400.2, transformer ratio and…MV-509 · MV view
Track what you have opened on My progress.All labs → · Ask the Copilot →

© 2026 Eng. Mannan Maqsood | Engineering Excellence Through Interactive Labs

VERIFY ALL FIGURES AGAINST CURRENT MANUFACTURER DATASHEETS AND LOCAL AUTHORITY REQUIREMENTS BEFORE DESIGN SIGN-OFF.

Share this pageFollow