Codes & standards 6
IEC 61936-1IEC 62271-202IEC 62271-200AS 2067AS/NZS 3000AS 6227
Regions 8
DubaiAbu DhabiSharjahN. EmiratesSaudiAustraliaNew ZealandInternational
Views
2D3D4D
Q&A145 HV bank questions →Site cases33 HV and MV site cases →
HV-502 · HV ACADEMY

Network Topology & Substation Layout Lab

Put a fault on a radial, open ring, closed ring or dual radial network and watch the supply drop out and come back. Compare reliability and automation, pick the right consumer substation scheme, then lay out the substation room with real clearances, walk through it in 3D, deliver the transformer and size the ventilation and oil bund. Click any for a plain-language explanation.

Open ring & NOPFLISRSAIDIRMU schemesIEC 61936-1IEC 62271-202Ventilation

1. Substation data

Pick your region first. It loads the usual network arrangement, substation type and transformer size. Everything can be changed.

Click any equipment
Front wall removed for viewing. Coloured floor zones are the clearances; the moving dots show cooling air from the low inlet to the high outlet.

Engineer's Notes: networks and substations

The open ring is the workhorse

Most urban cable networks in the GCC, Australia, New Zealand and Asia are open rings. Each substation has an RMU with two ring switches, and one switch on the ring is kept open as the NOP. A cable fault costs customers only the switching time, not the repair time.

Automation buys minutes

Manual switching takes about an hour once a crew is on site. Remote control from the control room cuts it to minutes, and automatic fault location, isolation and restoration (FLISR) to about a minute.

Plan the room early

The substation location, size and access are fixed by the utility's rules and the transformer delivery route. Agree them at concept stage: moving a substation late in design is one of the most expensive changes on a project.

Heat and oil drive the details

Transformer losses set the louver sizes or the air conditioning load. Oil volume sets the bund and fire separation. Dry-type or ester-filled transformers change both.

Frequently asked questions

What is a normally open point (NOP)?

An open switch in a ring network that splits the loop into two radial feeders. After a cable fault, the faulted section is isolated and the NOP is closed so that every substation is fed from one end or the other.

Why are urban HV networks built as open rings and not closed rings?

An open ring gives a second supply route using simple ring main units with load-break switches and simple overcurrent protection at the source. A closed ring avoids any interruption but needs circuit breakers and unit protection at every substation, which costs more.

What is SAIDI?

System Average Interruption Duration Index: the total customer minutes of interruption in a year divided by the number of customers. Network topology and how fast supply is restored after a fault have the biggest effect on it.

How big should a substation room be?

It depends on the RMU, the number and size of transformers, whether the LV board is in the same room, and the utility's clearances. Add equipment widths, the gaps between them, wall clearances and the operating aisle, then check door size, height, ventilation and oil containment against the utility's standard drawings.

How much ventilation does a transformer room need?

Enough to remove the transformer losses. For natural ventilation a common estimate is an inlet free area of about 0.18 x P / sqrt(H) square metres, where P is the losses in kW and H the height between inlet and outlet, with the outlet about 10 % larger. Hot climates often need forced ventilation.

Topics: radial network · open ring · normally open point · closed ring · unit protection · dual radial · FLISR · SAIDI · customer minutes lost · RMU · fuse-switch · HV metering · kiosk substation · substation room layout · clearances · transformer delivery · ventilation · oil bund · fire separation

Related labs

Standards and regions covered

Built around DEWA, ADDC (TAQA Distribution) and SEWA 11 kV and 33 kV distribution requirements, IEC 62271, IEC 60076, IEC 60909, IEC 60287, BS EN 50522, IEEE 80, AS 2067 and NZ Electricity (Safety) Regulations 2010. Engineers use it on projects in Dubai, Abu Dhabi, Sharjah and the Northern Emirates, and in Auckland, the rest of New Zealand and Australia. Always confirm the edition your authority or client has adopted before relying on a result.

NEXT STEP

Where to go from here

Related labs that pick up where this one ends.

HV Academy hubAll 17 high voltage labs in one learning path.HV ACADEMYRegional Regulation & Utility EngineCompare HV voltages, utilities, earthing, phase colours and standards for the UAE, Saudi Arabia, Australia,…HV-501 · previousHV Switchgear & Ring Main Unit LabSelect RMU ratings to IEC 62271, size HV fuses and relays, practise switching with live interlocks and…HV-503 · nextMV Systems & Network ExplorerFollow power from grid to building in 3D, compare radial, open and closed ring MV networks under fault, and…MV-501 · MV view
Track what you have opened on My progress.All labs → · Ask the Copilot →