MV-501 · Phase 1 Foundations

MV Systems & Network Explorer

Follow electricity from the power station to a socket in 3D, then break MV networks on purpose to see how each design restores supply, and find out what neutral earthing really does during an earth fault.

In short

  • Power is generated at about 11 to 24 kV, stepped up to transmission (132 to 500 kV), stepped down to MV distribution (11 to 33 kV), then to LV (400/230 V) at the building.
  • Most city MV networks are open rings. A fault drops one feeder briefly, and switching restores everyone in minutes. Radial networks leave customers off until the repair is done.
  • The neutral earthing method sets the earth fault current: tens of kA for solid earthing, a few hundred to about 1000 A with a resistor, and only a few amps with resonant earthing.
  • Australia's Victoria uses REFCL resonant earthing in bushfire areas. Resistance earthing at the primary substation is common in GCC and Asian 11 kV networks, but always check the utility's practice.

4D Grid Journey: power station to socket 3D 4D

Press play to follow the energy through each stage. The camera moves with it and the voltage changes for your region. You can also drag to look around and click any part of the scene.

15 kV
Generation
Drag: rotate · Wheel/pinch: zoom · Click: inspect

    Generation

    Voltage ladder for GCC

    Network Topology Simulator 2D Animated

    Pick a network design, click a cable section to fault it, then step through what happens: the protection trips, the crew or automation switches, and the cable is repaired. The table compares all four designs for the same fault.

    Faulted section: S2 (click a cable to change it)

    Compare designs for this fault

    DesignSubstations off at faultOff after switchingTypical restorationRelative costWhere it is used

    Neutral Earthing Simulator 2D Animated

    Choose how the MV system neutral is earthed, then apply an earth fault on phase A. The phasor diagram shows how the healthy phase voltages rise, and the results show the fault current and what the protection has to do.

    Earthing methods compared

    MethodEarth fault currentHealthy phase voltageSupply during faultTypical use
    SolidVery high (kA, near 3-phase level)Up to about 1.4 puTripsLV systems, some MV networks, transmission
    Low resistance (NER)Limited, often a few hundred to about 1000 AUp to about 1.7 puTripsCommon for 11 kV in the GCC, UK practice and much of Asia
    High resistanceLow, a few to tens of ampsAbout 1.73 puCan run with alarmIndustrial plants, generators
    Resonant (Petersen coil, REFCL)Very low, a few ampsAbout 1.73 puCan run, arcs self-extinguishOverhead networks in Europe, Victoria (AU) bushfire areas, some NZ networks
    IsolatedCapacitive charging current only1.73 pu or more (arcing overvoltages)Can run brieflySmall or legacy networks

    How does electricity get from the power station to a building?

    Generators produce power at around 11 to 24 kV. A generator step-up transformer raises it to transmission voltage, such as 400 kV in the UAE or 330 to 500 kV in eastern Australia, because higher voltage means lower current and lower losses over long distances. At grid substations it is stepped down to 132 kV or similar, then to MV (11 kV in most places) at primary or zone substations. MV cables run through the streets to distribution substations, where a transformer drops it to 400/230 V for the building's main LV board.

    PractitionerThe voltage at each level is regulated. On-load tap changers on the primary substation transformers hold the 11 kV busbar voltage, while distribution transformers only have off-circuit taps. That is why LV voltage complaints often need a tap change at the distribution transformer and a check of the MV voltage profile along the feeder.

    Radial, open ring or closed ring: which MV network is best?

    It depends on how much an outage costs compared with the cost of the network:

    • Radial: cheapest. It is used for rural overhead lines and small sites, where a fault leaves customers off until the repair.
    • Open ring: the standard for urban underground networks. It needs only RMUs with load break switches. A fault causes a short outage on one feeder, then switching restores supply.
    • Closed ring: no outage for a single cable fault, but it needs circuit breakers and unit protection at every substation. It is used for critical loads, airports and some CBD networks.
    • Automated ring (FLISR): an open ring with remote-controlled RMUs, FPIs and SCADA. Fault location, isolation and service restoration happens automatically, often in under a minute.

    ExpertUtilities measure reliability with SAIDI (average outage minutes per customer per year) and SAIFI (average interruptions per customer per year). Automating the open rings mainly cuts SAIDI, because most of the outage time in a manual open ring is the time to find the fault and send a crew to switch.

    What does neutral earthing do?

    On an MV system, the transformer star point (or an earthing transformer) can be connected to earth directly, through a resistor or reactor, or not at all. This sets how much current flows in an earth fault, the most common fault on cable networks. High fault current is easy to detect but causes more damage and higher touch voltages. Very low fault current is safer for fire and damage, but the healthy phases rise to line voltage to earth, so cables and equipment must be rated for that, and the protection has to be more sensitive.

    PractitionerThe earth fault current also sets the screen rating of MV cables (see MV-502) and the earth grid design of substations (MV-508). Always get the utility's maximum earth fault current and clearance time before designing either.

    Regional notes

    GCC

    Transmission is mainly 400 kV and 132 kV (220 kV in parts of Qatar and Oman), with 11 kV distribution in urban open rings fed from 132/11 kV or 33/11 kV substations. The GCC interconnection ties the national grids together at 400 kV. Saudi Arabia runs at 60 Hz with 380 kV transmission and 13.8 kV and 33 kV distribution.

    Australia

    The National Electricity Market runs 500, 330, 275 and 220 kV transmission in the east, with 132 and 66 kV subtransmission. Distribution is 11 kV and 22 kV, plus SWER lines in rural areas. REFCLs are required at specified zone substations in high bushfire risk areas of Victoria.

    New Zealand

    Transpower runs the 220 kV and 110 kV national grid, including the HVDC link between the islands. Lines companies run 33 kV subtransmission and 11 kV or 22 kV distribution.

    Asia

    India uses 765 and 400 kV transmission with 11, 22 and 33 kV distribution. Malaysia (TNB) uses 500, 275 and 132 kV with 11 to 33 kV distribution. Singapore's SP Group runs 400, 230 and 66 kV with 22 kV and 6.6 kV distribution.

    Test yourself

    0 / 10

    Ten questions on MV systems and networks. Pick an answer to see the explanation. Practise about 50 more MV-501 questions in the MV Question Bank.

    Frequently asked questions

    What is the difference between a radial and a ring MV network?
    A radial network feeds each substation from one direction only, so a cable fault leaves everyone beyond it off until the cable is repaired. A ring connects substations in a loop with a normally open point, so after a fault the faulted section is isolated and supply is restored from the other end in minutes. Most urban 11 kV networks are open rings.
    Why is the MV ring run open instead of closed?
    An open ring only needs simple overcurrent protection at the source and low-cost load break switches at each substation. Running a ring closed keeps supply on during a fault, but needs circuit breakers and unit protection such as differential or pilot wire protection at every substation, which costs much more.
    What are the main neutral earthing methods for MV systems?
    Solid earthing, low-resistance earthing through a neutral earthing resistor, high-resistance earthing, resonant earthing with a Petersen coil (arc suppression coil), and an isolated or unearthed neutral. They trade off earth fault current, overvoltage on healthy phases, touch voltage and the ability to keep supplying during an earth fault.
    What is a REFCL?
    A Rapid Earth Fault Current Limiter is an advanced resonant earthing system that drives the faulted phase voltage close to zero within milliseconds of an earth fault. Victoria, Australia requires REFCLs at specified zone substations in high bushfire risk areas to reduce the chance of a fault starting a fire.
    What are typical transmission voltages in the GCC?
    400 kV and 132 kV are the main transmission voltages in the UAE, with 220 kV also used in parts of the region such as Qatar and Oman. Saudi Arabia uses 380 kV with 132 kV and 110 kV. MV distribution is mainly 11 kV, or 13.8 kV and 33 kV in Saudi Arabia.

    Standards referenced

    • IEC 60038 Standard voltages
    • IEC 60071-1 Insulation co-ordination
    • IEC 60909 Short-circuit currents
    • IEEE C62.92 Neutral grounding

    Quick summary in your language

    Read this lab's key points in English, Urdu, Hindi or Arabic. The lab itself is in English.

    This lab follows power from the grid to a building in 3D and compares radial and ring MV networks under fault. See how each neutral earthing method changes the fault current.

    Project checks

    Map the normal source and tie positions, then examine a feeder or source outage. Identify the affected loads and switching constraints before assessing an alternative arrangement.

    NEXT STEP

    Where to go from here

    Related labs that pick up where this one ends.

    Medium Voltage hubAll 16 MV labs and the 788-question MV bank.MV HUBMV Cables & Accessories LabMV XLPE cable lab: 3D cable layers, IEC 60287 rating for 6.6 to 33 kV, voltage drop and short-circuit checks,…MV-502 · nextNetwork Topology & Substation Layout LabFault an 11 kV open ring and watch restoration in 4D, compare SAIDI by topology, then size a substation room…HV-502 · HV viewLV Switchgear Design LabCarry the design downstream to the LV panels.E-127
    Track what you have opened on My progress.All labs → · Ask the Copilot →