HV-507 · HV ACADEMY

Protection & Coordination Studio

Grade a real HV customer substation from the utility relay down to the LV feeder MCCB. Set curves on a live time-current chart or let the studio auto-grade, then fire faults at the cable, transformer, LV bus and feeder and watch which breaker trips first in 3D. Test transformer differential and restricted earth fault, and print the setting schedule. Click any for a plain-language explanation.

IEC 60255-151IEEE C37.112IEC 61869-250/5150N/51N87T64REFLSI

1. System data

Pick your region first. It loads the utility voltages, typical ratings, ambient, fault level, phase colours and standards. Everything can be changed.

Click any zone or device
Toggle the protection zones, then fire a fault. The fault current flows from the utility, and the device that should clear it flashes red.

Quick summary in your language

Read this lab's key points in English, Urdu, Hindi or Arabic. The lab itself is in English.

This lab grades HV relays, fuses and LV breakers on a time-current chart and tests faults in 4D. The breaker nearest the fault should trip first, so check the grading margins.

Engineer's Notes: protection coordination

Fast where it must be, slow where it should be

Good protection clears every fault quickly with the smallest possible outage. The device closest to the fault trips first; each device upstream waits a grading margin longer as backup. On a time-current chart that means curves stacked with clear gaps at every fault level that matters.

The transformer sits in the middle

The HV relay must protect the transformer against faults and through-fault damage, ride through magnetising inrush, and still wait for the LV ACB on LV faults. Its high-set element goes above the LV fault seen on HV and the inrush; its inverse element grades above the ACB.

Unit protection for bigger transformers

Differential (87T) and restricted earth fault (REF) only see faults inside their zone, so they trip instantly without grading. They are common on transformers above about 2.5 to 5 MVA and on critical supplies such as hospitals and data centres.

Know your network earthing

Earth fault protection depends completely on how the HV neutral is earthed. Solid, resistance, resonant and isolated systems need different relays and settings. Always get the utility earth fault level and earthing method before setting 51N.

Frequently asked questions

What grading margin is needed between protection relays?

A coordination time interval of about 0.3 to 0.4 s between numerical relays is common. It covers the downstream breaker opening time, relay overshoot and timing errors. Between a relay and a downstream LV breaker or fuse, smaller margins may be used, but utilities often state their own minimum.

Why does the HV relay need a high-set element above the LV fault current?

The high-set (instantaneous) element should trip quickly for HV faults but must not see faults on the LV side, which the LV breaker should clear. Setting it above about 1.3 times the LV terminal fault current referred to HV, and above transformer inrush, keeps it selective.

How does transformer differential protection avoid tripping on inrush?

Magnetising inrush flows only on the energised side, so it looks like an internal fault. Inrush is rich in second harmonic, so the relay blocks when the second harmonic exceeds a set percentage of the fundamental, typically 15 to 20 percent.

What is restricted earth fault protection?

Restricted earth fault (REF) compares the sum of the phase CTs with a CT in the transformer neutral. It only sees earth faults inside the protected winding, so it can be set very sensitive and fast. The high-impedance version needs a stabilising resistor and CTs with enough knee-point voltage.

Why use a short-time delay on the LV main ACB?

The short-time delay lets the downstream MCCB clear a feeder fault first, so only that feeder is lost. The ACB still clears a busbar fault after the delay, and the HV relay is graded above it as backup.

Topics: relay coordination · TCC · IDMT curves · TMS · high-set · grading margin · discrimination · inrush · transformer damage curve · ACB LSI · MCCB · 87T differential · bias characteristic · 2nd harmonic blocking · REF · stabilising resistor · metrosil · earth fault · network earthing

Related labs

Project checks

Plot the upstream and downstream relay behaviour for the applicable fault levels and settings. Confirm CT data, equipment withstand and utility requirements before accepting a grading margin.

NEXT STEP

Where to go from here

Related labs that pick up where this one ends.

HV Academy hubAll 17 high voltage labs in one learning path.HV ACADEMYFault Level & Short Circuit LabCalculate HV and LV fault levels to IEC 60909: peak, breaking and thermal currents, switchgear ratings,…HV-506 · previousHV Substation Earthing LabDesign an IEEE 80 earth grid, calculate GPR, touch and step voltages, see the surface potential in 3D, run a…HV-508 · nextMV Protection & Relay CoordinationPlot IEC IDMT relays, HV fuses and LV ACBs on one TCC chart, check grading margins, inrush and damage curves,…MV-507 · MV view
Track what you have opened on My progress.All labs → · Ask the Copilot →