Codes & standards 16
IEC 60909-0IEC 61439IEC 62271IEC 60909IEC 60865-1AS/NZS 3000
+10 more
IEC 60865IEC 62271-100AS/NZS 6143AS 6090AS 6227IEEE 551IEC 60949IEC 61439-1IEC 62271-200IEC 61641
Regions 8
DubaiAbu DhabiSharjahN. EmiratesSaudiAustraliaNew ZealandInternational
Views
2D3D4D
Q&A145 HV bank questions →Site cases33 HV and MV site cases →
HV-506 · HV ACADEMY

Fault Level & Short Circuit Lab

Follow the fault current from the utility RMU, through the HV cable and transformer, to the LV main switchboard. See the peak, breaking and thermal currents to IEC 60909, watch the asymmetrical waveform build up, check every switchboard rating, and see what the peak current does to busbars in 3D. Click any for a plain-language explanation.

IEC 60909-0Peak current κX/R and DCIEC 62271IEC 61439IEC 60865Earth faults

1. Supply and network data

Pick your region first. It loads the voltage, frequency, a typical declared fault level and X/R, and typical equipment ratings. Replace them with the values from your utility connection offer.

Click any part
Press the fault button to watch the current flow and the bars being pushed apart and pulled together. The middle bar carries the highest force. Movement is exaggerated for clarity.

Engineer's Notes: fault level and short circuit

Start with the utility data

Every short-circuit study starts with the fault level and X/R the network operator declares at the point of supply, both maximum and minimum. The maximum sets equipment ratings; the minimum checks that protection still trips fast enough.

The transformer sets the LV fault level

Seen from the LV side, upstream HV impedance shrinks by the square of the voltage ratio. The transformer impedance dominates, so transformer size and uk decide whether the LV board needs 50, 65 or 80 kA.

Peak current breaks things

The first peak, including the DC offset, can be over 2.5 times the rms fault current. It sets the making capacity of breakers and the mechanical force on busbars and supports, which grows with the square of the current.

Fault levels grow

New generation, network reinforcement and bigger transformers raise fault levels over the life of a building. Leave a margin and check again whenever a generator is paralleled with the grid.

Frequently asked questions

How do you calculate the fault level at an LV switchboard?

Add the source impedance from the utility fault level, the HV cable, the transformer impedance and the LV busduct, all referred to the LV voltage. Then Ik'' = c x Un / (sqrt(3) x Zk). The transformer impedance dominates, so a 1500 kVA, 6 % transformer gives roughly 35 kA at 400 V.

What is the difference between Ik'', ip, Ib and Ith?

Ik'' is the initial symmetrical rms current. ip is the highest instantaneous peak including the DC offset and sets the making and mechanical ratings. Ib is the current when the breaker contacts part and sets the breaking rating. Ith is the rms current with the same heating effect over the fault duration.

Why does the X/R ratio matter?

X/R sets how slowly the DC offset decays. A higher X/R gives a higher peak current and more DC at contact separation. IEC switchgear is tested with a 45 ms time constant, about X/R 14 at 50 Hz, so higher values need a special check.

Does a generator increase the fault level?

Yes. A synchronous generator running in parallel with the grid feeds its own fault current, typically 5 to 8 times its rated current at first. Every switchboard rating must be checked again before parallel generation is connected.

Why can an LV earth fault be higher than the three-phase fault?

With a Dyn transformer the zero-sequence impedance seen from the LV side is close to the transformer impedance only, while the HV source adds to the positive and negative sequence. Close to the transformer the single-phase fault can therefore equal or slightly exceed the three-phase value.

Topics: fault level · IEC 60909 · Ik'' · peak current · kappa factor · X/R ratio · DC time constant · breaking current · thermal equivalent current · switchgear kA rating · Icw and Ipk · transformer impedance · generator contribution · motor contribution · busbar forces · earth fault current · NER

Related labs

Standards and regions covered

Built around DEWA, ADDC (TAQA Distribution) and SEWA 11 kV and 33 kV distribution requirements, IEC 62271, IEC 60076, IEC 60909, IEC 60287, BS EN 50522, IEEE 80, AS 2067 and NZ Electricity (Safety) Regulations 2010. Engineers use it on projects in Dubai, Abu Dhabi, Sharjah and the Northern Emirates, and in Auckland, the rest of New Zealand and Australia. Always confirm the edition your authority or client has adopted before relying on a result.

NEXT STEP

Where to go from here

Related labs that pick up where this one ends.

HV Academy hubAll 17 high voltage labs in one learning path.HV ACADEMYHV Cable Engineering LabRate 11 to 33 kV cables to IEC 60287, check short-circuit withstand to IEC 60949, compare laying methods and…HV-505 · previousProtection & Coordination StudioGrade HV relays, fuses and LV breakers on a live time-current chart, simulate faults in 4D, test 87T…HV-507 · nextShort Circuit & Load Flow StudioIEC 60909 short circuit from the 11 kV source to the final DB: three-phase and earth fault levels, peak…MV-506 · MV view
Track what you have opened on My progress.All labs → · Ask the Copilot →