What is the IEC 60909 method?
IEC 60909 replaces all the sources with one equivalent voltage source at the fault, c·Un/√3, and adds up the positive-sequence impedances of everything between the source and the fault. The voltage factor c covers the fact that the real network voltage can be higher than nominal. For maximum currents, cmax is 1.10 for MV and 1.05 (or 1.10) for LV systems. For minimum currents (used for protection sensitivity), cmin is 0.95 at LV and 1.00 at MV.
ExpertThe full method also applies an impedance correction factor KT = 0.95·cmax/(1 + 0.6·xT) to network transformers, and uses cable resistances at 20 °C for maximum currents and at the end-of-fault temperature for minimum currents. This studio applies KT in Expert mode.
Why is peak current important?
The first peak of a fault current can be up to 2.8 times the RMS value because of the DC offset. Busbars, breakers' making capacity and cable supports have to survive these electromagnetic forces. The ratio κ depends on R/X: close to a large transformer, X/R is high and κ approaches 1.8 to 1.9.
How do earth fault levels differ?
In a TN system with a Dyn11 transformer, a phase-to-earth fault at the LV terminals can be slightly higher than the three-phase fault, because the delta winding gives a low zero-sequence impedance. Further out, the protective conductor adds impedance and the earth fault current falls faster. The minimum earth fault current at the end of a circuit decides whether the breaker trips fast enough for automatic disconnection.
Regional notes
GCC
Utilities publish the maximum MV fault level for design (for example 20 to 31.5 kA at 11 kV) and often specify LV main boards at 50 to 65 kA for large transformers. Check the utility's design values for LV fault level at the incoming terminals.
Australia and New Zealand
AS/NZS 3000 requires the fault level at the main switchboard to be determined. Network operators publish prospective fault currents at the point of supply. AS/NZS 3008.1 helps with cable impedances.
Asia
IEC 60909 is the common basis. Utilities publish the prospective fault level at the point of supply for consumer substations.