MV-506 · Phase 2 Design & analysis

Short Circuit & Load Flow Studio

Build a supply chain from the 11 kV source to a final distribution board. The studio calculates IEC 60909 fault levels at every bus, animates the fault current path, checks your switchgear ratings and plots the voltage profile under load.

In short

  • IEC 60909 uses an equivalent voltage source c·Un/√3 at the fault, with c = 1.1 for maximum MV faults and 1.05 or 1.10 for LV.
  • Initial fault current Ik" = c·Un / (√3·|Zk|), and peak current ip = κ·√2·Ik", with κ = 1.02 + 0.98e−3R/X.
  • At the LV board the transformer impedance dominates. A 1500 kVA, 6.25% unit gives about 33 to 35 kA at 400 V.
  • Busduct and cable impedance bring the fault level down quickly, which is why final DBs can use lower-rated breakers.
  • Running motors add to the fault current for the first few cycles, so include them when checking peak and making ratings.

Fault Level Studio 2D Animated

Set each element in the chain. Click a bus in the diagram (or use the buttons) to put a fault there and watch the fault current flow from the source.

Results

Switchgear rating check

    Fault level at each bus

    Load Flow & Voltage Profile 2D

    Add load at each board and see how the voltage falls along the chain. The transformer tap can lift the whole profile.

    Green band: ±6% around nominal, a common design target. Statutory supply limits are often wider (for example +10%/-6% or ±10%). Many designs also limit the drop from the origin to the final circuit to about 4 to 5%.

    What is the IEC 60909 method?

    IEC 60909 replaces all the sources with one equivalent voltage source at the fault, c·Un/√3, and adds up the positive-sequence impedances of everything between the source and the fault. The voltage factor c covers the fact that the real network voltage can be higher than nominal. For maximum currents, cmax is 1.10 for MV and 1.05 (or 1.10) for LV systems. For minimum currents (used for protection sensitivity), cmin is 0.95 at LV and 1.00 at MV.

    ExpertThe full method also applies an impedance correction factor KT = 0.95·cmax/(1 + 0.6·xT) to network transformers, and uses cable resistances at 20 °C for maximum currents and at the end-of-fault temperature for minimum currents. This studio applies KT in Expert mode.

    Why is peak current important?

    The first peak of a fault current can be up to 2.8 times the RMS value because of the DC offset. Busbars, breakers' making capacity and cable supports have to survive these electromagnetic forces. The ratio κ depends on R/X: close to a large transformer, X/R is high and κ approaches 1.8 to 1.9.

    How do earth fault levels differ?

    In a TN system with a Dyn11 transformer, a phase-to-earth fault at the LV terminals can be slightly higher than the three-phase fault, because the delta winding gives a low zero-sequence impedance. Further out, the protective conductor adds impedance and the earth fault current falls faster. The minimum earth fault current at the end of a circuit decides whether the breaker trips fast enough for automatic disconnection.

    Regional notes

    GCC

    Utilities publish the maximum MV fault level for design (for example 20 to 31.5 kA at 11 kV) and often specify LV main boards at 50 to 65 kA for large transformers. Check the utility's design values for LV fault level at the incoming terminals.

    Australia and New Zealand

    AS/NZS 3000 requires the fault level at the main switchboard to be determined. Network operators publish prospective fault currents at the point of supply. AS/NZS 3008.1 helps with cable impedances.

    Asia

    IEC 60909 is the common basis. Utilities publish the prospective fault level at the point of supply for consumer substations.

    Test yourself

    0 / 8

    8 questions. Pick an answer to see the explanation. Practise about 50 more MV-506 questions in the MV Question Bank.

    Frequently asked questions

    How do I calculate the fault level at a transformer LV terminal?
    A quick estimate is Ik = In / uk, where In is the LV full-load current and uk is the per-unit impedance. A 1500 kVA, 6% transformer at 400 V has In = 2165 A, so Ik is about 36 kA with an infinite source. The MV source impedance and the c factor change this slightly, which the studio includes.
    What is the c factor in IEC 60909?
    The voltage factor c scales the nominal voltage to cover the highest likely operating voltage. For maximum fault currents it is 1.10 at MV and 1.05 or 1.10 at LV, depending on the voltage tolerance.
    What is the difference between Icu, Ics and Icw?
    Icu is a breaker's ultimate breaking capacity, Ics its service breaking capacity (it can still be used afterwards), and Icw the short-time withstand current a board or breaker can carry for a set time, usually 1 s, so downstream devices can clear first.
    Do motors contribute to fault current?
    Yes. Running induction motors feed fault current for the first few cycles, roughly their locked-rotor current. IEC 60909 includes them in Ik" and ip, but they decay quickly.

    Standards referenced

    • IEC 60909-0 Short-circuit currents
    • IEC 60947-2 LV circuit-breakers
    • IEC 61439-1 LV switchgear assemblies
    • AS/NZS 3000 and AS/NZS 3008.1 (AU/NZ)

    Quick summary in your language

    Read this lab's key points in English, Urdu, Hindi or Arabic. The lab itself is in English.

    This lab calculates short circuit levels from the 11 kV source down to the final board, plus motor contribution and voltage profile. Check that every device is rated for the fault at its point.

    Project checks

    Treat load flow and short-circuit calculations as separate studies with shared network inputs. Verify the source lineup, transformer data and modeled switching states before comparing either result with limits.

    NEXT STEP

    Where to go from here

    Related labs that pick up where this one ends.

    Medium Voltage hubAll 16 MV labs and the 788-question MV bank.MV HUBSubstation Design & Layout 3DDesign an 11 kV building substation or kiosk in 3D: operating clearances, doors, transformer room…MV-505 · previousMV Protection & Relay CoordinationPlot IEC IDMT relays, HV fuses and LV ACBs on one TCC chart, check grading margins, inrush and damage curves,…MV-507 · nextFault Level & Short Circuit LabCalculate HV and LV fault levels to IEC 60909: peak, breaking and thermal currents, switchgear ratings,…HV-506 · HV view
    Track what you have opened on My progress.All labs → · Ask the Copilot →