Chilled Water Pipe Sizing & Pump Head Lab

Turn the cooling load into a chilled water flow, size the riser floor by floor and the branches to the far AHU, then add the coil, control valve, chiller or ETS and strainer to get the pump head. Size the pump motor and the expansion vessel, and see the pressure profile around the index circuit.

ASHRAE FundamentalsCIBSE Guide CEmpower and Emicool ETSDubai Green Building RegulationsAS/NZS 3500Darcy-Colebrook

How to use: enter the load and the building, and the riser sizes itself. Use the pipe sizer below for any single flow. Tap i for plain explanations.

1. Load and building

Direct return riser feeding one AHU or FCU group per floor.

Cooling load
Pipework
Equipment pressure drops

2. Riser and index circuit

Pipe sizes floor by floor, colour shows velocity. 4D shows the pressure profile around the index circuit.

3. Checks

    4. Pipe sizer for any flow

    5. Index circuit

    6. How it works

    Flow from load

    Flow = load / (ρ × cp × ΔT). For water, 1 L/s carries about 4.19 kW per kelvin. A wider ΔT, as district cooling providers ask for, cuts the flow, the pipe sizes and the pump energy.

    Sizing

    Each pipe gets the smallest nominal size whose friction is at or below the limit and whose velocity is within the band for its size: about 1.2 m/s up to DN50 and up to 3 m/s for large mains. Friction is Darcy-Weisbach with the Colebrook friction factor at the water temperature.

    Pump head

    The index circuit is the path to the top floor in a direct return riser. Pump head adds supply and return pipe friction with a fittings allowance, the coil, the control valve, the chiller or ETS heat exchanger and the strainer. A valve authority of 0.5 means the valve drop equals the rest of its branch.

    Expansion

    Chilled water expands when the plant is off and warms to room temperature. The vessel is sized from the system volume, the expansion from 4 °C to the maximum ambient, and the fill and maximum pressures.

    Learning and checking tool. Final pipe sizing and pump selection need the equipment data, the district cooling provider's rules where relevant, and the design software results.

    Quick summary in your language

    Read this lab's key points in English, Urdu, Hindi or Arabic. The lab itself is in English.

    This lab sizes chilled water pipes floor by floor, works out pump head along the index circuit and sizes the expansion vessel. Check the control valve authority so the system can be balanced.

    About this lab: Chilled Water Pipe Sizing & Pump Head Lab

    Chilled Water Pipe Sizing & Pump Head Lab

    Size chilled water pipes from the cooling load and ΔT, floor by floor up the riser, then work out the index circuit pump head, pump power, control valve drop and expansion vessel.

    Topics you can explore

    • Flow from load and ΔT
    • Friction and velocity limits
    • Riser sizing floor by floor
    • Index circuit and pump head
    • Control valve authority
    • District cooling ETS
    • Expansion vessel

    Practical engineering example

    A 3,500 kW office tower at 5.5 K needs about 152 L/s. With 90% diversity the riser starts at DN250, and with 45 kPa coils, a 65 kPa chiller and 50% fittings the pump head comes out around 25 to 30 m.

    Developed by Eng. Mannan Maqsood. Verify against current project requirements and the applicable authority rules.

    Project checks

    Establish the selected coil flow, design temperature difference and critical circuit before sizing chilled-water piping or checking head. Verify valve, strainer and equipment losses against the approved hydraulic arrangement.

    NEXT STEP

    Where to go from here

    Related labs that pick up where this one ends.

    Duct Sizing & Fan Static LabAir side of the same AHUs.HVAC-403 →HVAC Virtual Engineering LabChillers, AHUs and controls in 3D.HVAC-401 →HVAC Equipment SimulatorWiring, controls and fault finding.HVAC-402 →Clash Detection LabCoordinate risers and mains.E-121 →
    Your work in each lab is saved in this browser.Save or move my progress · All 127 labs · Ask the Copilot