Codes & standards 13
IEC 60099-4IEC 60071-1IEC 60071IEC 61936-1IEC 60815IEC 60071-2
+7 more
AS 1824AS/NZS 7000AS 6009AS 2067IEC 62305IEEE 1410IEEE 1313.2
Regions 8
DubaiAbu DhabiSharjahN. EmiratesSaudiAustraliaNew ZealandInternational
Views
3D4D
Q&A145 HV bank questions →Site cases33 HV and MV site cases →
HV-509 · HV ACADEMY

Insulation Coordination & Surge Lab

Send a lightning surge down an overhead line into a cable and watch it reflect and build up at the transformer. Add arresters at either end, pick an arrester rating that survives earth faults, check the protective margin against the equipment insulation level, find how far the arrester can be from the transformer, and check clearances and creepage. Click any for a plain-language explanation.

IEC 60071IEC 60099-4Travelling wavesLIWL / BILTOVIEC 61936-1IEC 60815

1. System and surge data

Pick your region first. It loads the usual equipment voltage, system earthing, fault clearing time, lightning activity and altitude. Replace them with your project values.

Click any part
Press "Lightning strike" to send a surge along the line. Arresters glow when they conduct and the surge drains to earth; without protection the transformer bushings flash over.

Engineer's Notes: insulation coordination

Match stresses to strengths

Insulation coordination means choosing equipment insulation levels and protective devices so that the overvoltages the network can produce never exceed what the insulation can withstand, with a sensible safety margin. Arresters set the stress; the LIWL sets the strength.

Earthing sets the arrester rating

During an earth fault the healthy phases rise towards line voltage on resistance-earthed and unearthed networks. The arrester must ride through that temporary overvoltage for as long as the fault lasts, which is why ratings differ so much between regions.

Distance eats the margin

Surges travel at hundreds of metres per microsecond and reflect at every change of impedance. The voltage at a transformer a few metres from its arrester can be well above the arrester's residual voltage, and the far end of a cable can nearly double it.

Clearances and creepage

Air clearances protect against flashover from impulses; creepage protects against tracking under pollution. Coastal, desert dust and industrial sites need longer creepage, and high altitudes need larger clearances.

Frequently asked questions

Why is a surge arrester needed where an overhead line meets a cable?

The cable has a much lower surge impedance than the line, so a lightning surge reflects at the junction and again at the far end of the cable, where the voltage can almost double. An arrester at the transition clamps the voltage entering the cable and protects the cable and the equipment at its end.

How do I choose the arrester rating Uc?

Uc must be at least the highest continuous phase-to-earth voltage, and the arrester must survive the temporary overvoltage on the healthy phases during an earth fault for as long as the fault lasts. On solidly earthed systems Uc can be close to Um divided by root 3; on unearthed or resonant earthed systems with long faults, Uc should be at least Um.

What is the protective margin?

The ratio of the equipment lightning impulse withstand level (LIWL or BIL) to the arrester residual voltage at nominal discharge current. IEC 60071-2 applies a safety factor of 1.15 for internal insulation, so a margin of at least about 1.2 is usually required, more if the arrester is some distance from the equipment.

Why does the distance between the arrester and the transformer matter?

A surge reflects at the transformer and the voltage there keeps rising until the reflected wave reaches the arrester and comes back. The extra voltage is roughly 2 x steepness x distance / wave speed, so a few metres of separation or long arrester leads can use up the whole margin.

What are the standard insulation levels for 11 kV equipment?

For Um 12 kV, IEC 60071-1 gives a power-frequency withstand of 28 kV and a lightning impulse withstand of 60 kV (list 1) or 75 kV (list 2). Many utilities specify list 2 or higher for equipment connected to overhead lines.

Topics: insulation coordination · surge arrester · Uc · Ur · TOV · residual voltage · protective margin · protective distance · LIWL · BIL · travelling waves · surge impedance · reflection · Bewley lattice · air clearance · creepage · pollution · altitude correction · ground flash density

Related labs

Standards and regions covered

Built around DEWA, ADDC (TAQA Distribution) and SEWA 11 kV and 33 kV distribution requirements, IEC 62271, IEC 60076, IEC 60909, IEC 60287, BS EN 50522, IEEE 80, AS 2067 and NZ Electricity (Safety) Regulations 2010. Engineers use it on projects in Dubai, Abu Dhabi, Sharjah and the Northern Emirates, and in Auckland, the rest of New Zealand and Australia. Always confirm the edition your authority or client has adopted before relying on a result.

NEXT STEP

Where to go from here

Related labs that pick up where this one ends.

HV Academy hubAll 17 high voltage labs in one learning path.HV ACADEMYHV Substation Earthing LabDesign an IEEE 80 earth grid, calculate GPR, touch and step voltages, see the surface potential in 3D, run a…HV-508 · previousGeneration & Renewables Interconnection LabSynchronise a generator on a live synchroscope, check voltage rise and hosting capacity, test loss-of-mains…HV-510 · nextPower Quality & Reactive CompensationBuild waveforms from harmonics and see THD and K-factor live, size a PF correction bank, check resonance and…MV-512 · MV view
Track what you have opened on My progress.All labs → · Ask the Copilot →