Codes & standards 9
IEC 60599IEC 60076-7IEC 60422ISO 55000IEC 60270IEC 62271
+3 more
AS 6059NFPA 70BIEC 60156
Regions 8
DubaiAbu DhabiSharjahN. EmiratesSaudiAustraliaNew ZealandInternational
Views
3D4D5D
Q&A145 HV bank questions →Site cases4 cases linked to this lab →
HV-514 · HV ACADEMY

Asset Management & Diagnostics Lab

Find out what is happening inside a transformer or switchboard before it fails. Plot DGA results on the Duval triangle, see how load and heat eat into insulation life, read a thermal image, grade partial discharge readings, and turn it all into a health index with a life projection. Click any for a plain-language explanation.

Duval triangleIEC 60599IEC 60076-7IEC 60422ThermographyTEV PDHealth index

1. Asset data

Pick your region first. It sets a typical weighted ambient temperature. Then enter the asset age and latest oil test results.

Click any monitoring point
Sampling valve, Buchholz relay, temperature indicator, bushings, PD sensor and cable terminations. Switch on the thermal camera to see temperatures.

Engineer's Notes: asset condition and diagnostics

The oil tells the story

Faults inside a transformer break down oil and paper into characteristic gases. Regular DGA, interpreted with the Duval triangle and IEC 60599 ratios, finds overheating, partial discharge and arcing long before a trip.

Heat is the clock

Paper insulation ages with temperature. The hot-spot, driven by load and ambient, sets how fast the clock runs. In hot climates, summer peaks can use more life than the rest of the year.

Look and listen

Thermography finds loose and corroded joints; TEV and ultrasonic surveys find partial discharge in switchgear and terminations. Both are quick, non-intrusive and done with the equipment in service.

From data to decisions

A health index combines all the evidence into one score per asset, so maintenance and replacement money goes where the risk is highest.

Frequently asked questions

How do you read a Duval triangle?

Take the three gases methane, ethylene and acetylene, express each as a percentage of their sum, and plot the point on the triangle. The zone it falls in (PD, T1, T2, T3, D1, D2 or DT) indicates the likely fault type. Only use it when gas levels are above normal.

What does acetylene in transformer oil mean?

Acetylene forms at very high temperatures, mostly in electrical arcs and sparking. Even a few ppm in a transformer without an on-load tap changer is a warning sign that needs a quick resample and investigation.

How fast does transformer insulation age?

IEC 60076-7 sets the normal ageing rate at a 98 °C hot-spot for non-upgraded paper. Every 6 K above that doubles the ageing rate, so a few hours of overload on a hot day can use days of normal life.

What do thermography temperature differences mean?

Compare a component with a similar one under the same load. A rise of 1 to 3 K suggests a possible problem, 4 to 15 K a probable deficiency, and over 15 K a major one that should be repaired soon.

What is a transformer health index?

A score, usually 0 to 100, that combines DGA, oil quality, partial discharge, thermography, age, loading and maintenance history. Utilities use it to rank assets and plan maintenance and replacement.

Topics: dissolved gas analysis · Duval triangle · IEC 60599 · IEEE C57.104 · key gases · CO2/CO ratio · hot-spot · relative ageing · loss of life · remaining life · thermography · NETA · partial discharge · TEV · ultrasonic · oil BDV · moisture · health index · condition-based maintenance · RCM

Related labs

Standards and regions covered

Built around DEWA, ADDC (TAQA Distribution) and SEWA 11 kV and 33 kV distribution requirements, IEC 62271, IEC 60076, IEC 60909, IEC 60287, BS EN 50522, IEEE 80, AS 2067 and NZ Electricity (Safety) Regulations 2010. Engineers use it on projects in Dubai, Abu Dhabi, Sharjah and the Northern Emirates, and in Auckland, the rest of New Zealand and Australia. Always confirm the edition your authority or client has adopted before relying on a result.

NEXT STEP

Where to go from here

Related labs that pick up where this one ends.

HV Academy hubAll 17 high voltage labs in one learning path.HV ACADEMYAuthority Submission & Energisation LabEstimate maximum demand, follow the utility approval process by region, plan the critical path to…HV-513 · previousPrimary Substations & GIS LabCompare busbar schemes in 4D, GIS vs AIS footprint, SF6 density and leakage, N-1 transformer capacity and a…HV-515 · nextCondition Monitoring & Failure ForensicsRead DGA on an interactive Duval Triangle, classify thermography hot spots, read partial discharge trends and…MV-515 · MV view
Track what you have opened on My progress.All labs → · Ask the Copilot →