Pump & Fan Affinity Laws and VSD Savings Lab

See the affinity laws at work: flow follows speed, pressure follows speed squared and power follows speed cubed. Put a pump or fan on its system curve, run it through a real day of part load and compare throttling, bypass and variable speed control for energy, cost and payback.

Affinity lawsASHRAE 90.1EN 16798IEC 61800-9Dubai Building CodeNZBC H1

How to use: enter the design duty, the share of the head that stays fixed (static lift or the differential pressure setpoint) and pick a daily load profile. Tap i for help.

1. Inputs

Machine and duty
Operation and cost

2. Curves and part load

Machine curves at reduced speed with the system curve, power for each control method, and a day of operation.

3. Checks

    4. Annual energy by control method

    5. Hour by hour on the design day

    6. How it works

    Affinity laws

    For the same machine at a new speed: flow changes in proportion to speed, pressure with speed squared and power with speed cubed. At 80% speed a pump delivers 80% flow at 64% head for about 51% of the power. That cube is why VSDs save so much on part load.

    System curve and the fixed part

    The system needs pressure to push the flow through pipes or ducts, rising with flow squared, plus a fixed part that does not fall with flow: static lift in an open system, or the differential pressure setpoint across the index circuit in a closed chilled water system. The bigger the fixed part, the less the VSD can slow down and the smaller the saving.

    Control methods

    Throttling closes a valve or damper and rides back up the fixed speed curve: flow drops but power only falls a little. Bypass keeps the pump at full flow and sends the surplus round a bypass, so power stays flat. A VSD slows the machine to match the system curve. ASHRAE 90.1 and the Dubai Building Code expect variable flow with VSDs on larger pumps and fans.

    Model uses a typical curve shape and efficiency that holds along each affinity parabola. Use the maker's curves and a measured load profile for a real business case.

    Quick summary in your language

    Read this lab's key points in English, Urdu, Hindi or Arabic. The lab itself is in English.

    This lab applies the pump and fan affinity laws and compares throttling, bypass and VSD control over a day. A small cut in speed saves a lot of power, which is why VSDs pay back quickly.

    About this lab: Pump & Fan Affinity Laws and VSD Savings Lab

    Pump & Fan Affinity Laws and VSD Savings Lab

    Apply the pump and fan affinity laws, put the machine on its system curve with a fixed pressure part, and compare throttling, bypass and VSD control over a real daily load profile for energy, cost and payback.

    Topics you can explore

    • Affinity laws
    • Pump and fan curves
    • System curves with fixed pressure
    • Throttling and bypass control
    • VSD speed and efficiency
    • Daily load profiles
    • Payback

    Practical engineering example

    A chilled water pump for 60 L/s at 250 kPa with 30% fixed pressure needs about 21 kW at design. On an office cooling day averaging 73% flow for 300 days it uses about 66,500 kWh a year with throttling control. With a VSD it uses about 40,800 kWh, 39% less, which at 0.45 per kWh pays back a 28,000 drive in about 2.4 years.

    Developed by Eng. Mannan Maqsood. Verify against current project requirements and the applicable authority rules.

    Project checks

    Use affinity laws as a screen for related operating points, then check the actual system curve and equipment limits. Confirm that savings estimates retain the flow and pressure required by the service.

    NEXT STEP

    Where to go from here

    Related labs that pick up where this one ends.

    Plant Noise LabSlower fans are quieter too.HVAC-409 →Energy Audit & Payback LabAdd the VSD to an audit package.E-140 →CHW Pipe Sizing LabWork out the pump head first.HVAC-404 →Harmonics LabDrive harmonics on the board.E-130 →
    Your work in each lab is saved in this browser.Save or move my progress · All 127 labs · Ask the Copilot