MV-503 · Phase 1 Foundations

RMU & MV Switchgear Lab

Take apart an 11 kV ring main unit in 3D, operate it through its interlocks, play real switching sequences step by step, and size the switchgear for your project and region.

In short

  • A ring main unit (RMU) is compact, sealed MV switchgear. It usually has two ring cable switches and one transformer feeder, rated 12 kV for 11 kV systems.
  • Configurations are written as letters: C = cable switch, F = fuse-switch, V = vacuum circuit breaker. So CCF means two ring switches and a fused transformer feeder.
  • Mechanical interlocks stop you earthing a closed switch, closing onto an applied earth, or opening a cable cover before the cable is earthed.
  • Specify to IEC 62271-200: LSC2, PM partitions, an IAC class such as AFL 20 kA 1 s, and a short-time rating at or above the network fault level.

3D RMU Explorer 3D

Drag to rotate, scroll or pinch to zoom, and click any part to see what it does. Use x-ray to see inside the gas tank, or explode the unit to pull it apart.

CCF · 2 ring switches + fused transformer feeder
Drag: rotate · Wheel/pinch: zoom · Click: inspect
The configuration you pick here is also used by the interlock simulator and the 4D sequences.

Click a part

Pick any part of the RMU to learn what it does. Switch the level at the top to get more technical detail.

Interlock Simulator 2D

Operate each functional unit like you would on site. The mechanical interlocks behave like the real thing, so try the wrong order and see what gets blocked. Faults and wrong operations go in the event log.

Event log

    4D Switching Sequences 3D 4D

    Each sequence runs on the 3D RMU over time. Watch the operating handle, the mimic diagram, the VPIS lamps and the cable cover change as each step happens. One sequence shows what goes wrong when a step is skipped.

    T + 00:00

      RMU Specification Configurator Calc

      Enter the network data and transformer size. The configurator works out the IEC 62271 ratings, suggests transformer feeder protection and writes a spec summary you can paste into a datasheet.

      Spec summary

      Regional notes

        What is a ring main unit (RMU)?

        A ring main unit is compact, factory-built medium voltage switchgear used in distribution substations. A typical 11 kV RMU has two load break switches for the ring cables coming in and going out, and one transformer feeder that supplies the substation transformer. Everything that carries high voltage sits in a sealed tank, filled with SF6 gas or, in newer designs, dry air or solid insulation. That makes the unit small, low maintenance and safe to stand in front of.

        Urban MV networks are laid as rings but run open at one point, the normally open point (NOP). If one cable section fails, the RMUs either side are switched to isolate it, and the NOP is closed to feed customers from the other end. You can try this on the MV Hub network simulator.

        PractitionerRing switches are usually rated 630 A, with a short-time rating of 16 kA, 20 kA or 25 kA for 1 s or 3 s at 12 kV. Transformer feeders are fuse-switch combinations to IEC 62271-105 (about 200 A rated) or vacuum circuit breakers to IEC 62271-100 with a self-powered or auxiliary-powered relay.

        ExpertCheck the switch class in IEC 62271-103 (E1/E2 electrical endurance, M1/M2 mechanical endurance) and the earthing switch class in IEC 62271-102 (E0, E1, E2 for short-circuit making). E2 earthing switches can close onto a live circuit more than once without needing maintenance, which matters for the operating error you can simulate above.

        What are the functional units in an RMU?

        LetterFunctional unitMain use
        CCable switch (load break switch + earth switch)Incoming and outgoing ring cables
        FFuse-switch combinationTransformer feeder, typically up to about 1000 to 1250 kVA at 11 kV
        VVacuum circuit breaker + relayLarger transformers, MV feeders, or where selectivity or SCADA tripping is needed
        DDirect cable connection (no switch)Some utilities use it for a solid cable tee
        MMetering unit (CTs and VTs)MV metering for bulk supply customers

        How do RMU interlocks keep people safe?

        Each cable switch in an RMU is usually a three-position switch: closed, open and earthed. Because it is one mechanism, it physically cannot be closed and earthed at the same time. On top of that, mechanical interlocks control the order of operation:

        • The earth position can only be reached from open, never straight from closed.
        • The cable compartment cover can only be removed when the earth switch is closed.
        • The switch cannot leave the earth position while the cable cover is off.
        • On a fuse-switch, a blown fuse striker trips all three phases and the fuses can only be reached with both sides earthed.
        • On a breaker unit, the disconnector can only be operated with the circuit breaker open.

        Interlocks do not know whether the far end of a cable is live. That is why you always check the voltage presence indicators (VPIS) before earthing, and why switching programs coordinate both ends of a cable.

        What do LSC2, PM and IAC AFL mean?

        These are IEC 62271-200 classifications that belong on every RMU datasheet:

        • LSC2 (loss of service continuity): when you open one unit's cable compartment, the busbar and the other units can stay in service. Older documents also refer to LSC2A and LSC2B.
        • PM (partition class): metallic partitions and shutters between live parts and the open compartment. PI means insulating partitions.
        • IAC AFL 20 kA 1 s: internal arc classified for accessibility A (authorised staff), tested on the Front and Lateral sides at 20 kA for 1 s. Add R if the rear is accessible. Use B where the public can reach the enclosure, as with many kiosks.

        ExpertThe internal arc test assumes a defined room layout and gas exhaust path. If your substation room is smaller, has a lower ceiling or vents differently from the tested setup, the IAC rating may not apply as installed. Ask the manufacturer for the minimum room dimensions, the pressure relief direction and the pressure rise calculation for the room.

        SF6 vs SF6-free RMUs: what is changing?

        SF6 is an excellent insulating gas but a very strong greenhouse gas. Regulation (EU) 2024/573 bans SF6 in new MV switchgear up to 24 kV from 2026, and up to 52 kV from 2030, with limited exceptions. Most major manufacturers now offer SF6-free RMUs that use vacuum interrupters with clean air, dry air or solid insulation. Outside the EU, utilities in the GCC, Australia, New Zealand and Asia are at different stages, so check whether the utility has approved the SF6-free model you want to specify.

        Fuse-switch or circuit breaker for the transformer feeder?

        Fuses are simple, fast and cheap, and they limit fault energy well. Circuit breakers with relays give adjustable protection, earth fault sensitivity, remote tripping and easier coordination with the LV main breaker. A practical rule:

        • Up to about 1000 to 1250 kVA at 11 kV, a fuse-switch is common and usually accepted by utilities.
        • Above that, or where you need selectivity, SCADA tripping, or transformer temperature and Buchholz trips, use a vacuum circuit breaker with a relay.
        • Pick the fuse rating from the manufacturer's selection table so it rides through the transformer inrush (often about 10 to 12 times full-load current for 0.1 s) and still clears an LV terminal fault quickly.

        Regional notes

        GCC

        Expect high ambient temperatures, dust and humidity. Check the derating at 50 °C, specify anti-condensation heaters, and only use RMU models on the utility's approved list (for example DEWA, ADDC/AADC, SEWA, KAHRAMAA or MEW). Saudi Arabia runs at 60 Hz with 13.8 kV and 33 kV networks under SEC specifications.

        Australia

        RMUs are specified to AS 62271.200 (identical to IEC 62271-200), with substation design to AS 2067 and the network operator's own standards. Pad-mount substations are common, so check the IAC class for public access.

        New Zealand

        The lines company (Vector, Orion, Wellington Electricity and others) sets the approved equipment and switching rules. Work under the Electricity (Safety) Regulations 2010 and the EEA Safety Manual - Electricity Industry (SM-EI).

        Asia

        Utilities such as TNB, SP Group, the Indian DISCOMs and K-Electric publish their own RMU specifications. 22 kV is the main voltage in Singapore, and 11 kV, 22 kV and 33 kV are all used in Malaysia and India.

        Checks before energising an RMU

        • Factory routine test certificates are reviewed, and the SF6 or gas pressure gauge is in the green zone.
        • Cable tests are complete (for example VLF withstand or tan delta), with phasing checked end to end.
        • Cable terminations are torqued, cable screens are earthed, and cable covers are fitted.
        • Interlocks have been operated through every position, and the VPIS is tested with a phase comparator.
        • Protection settings are applied and secondary injection tested (V units), or the fuse ratings match the approved design (F units).
        • The substation earth is tested, and the room is clean and dry, with the pressure relief path clear.

        Full test procedures are coming in MV-509 MV Testing & Commissioning Lab.

        Test yourself

        0 / 10

        Ten questions on RMUs and MV switchgear. Pick an answer to see the explanation. Practise about 50 more MV-503 questions in the MV Question Bank.

        Frequently asked questions

        What is a ring main unit (RMU)?
        A ring main unit is compact, factory-assembled medium voltage switchgear, usually rated 12 kV to 36 kV, with two or more load break switches for the incoming and outgoing ring cables and one or more transformer feeder units protected by fuses or a circuit breaker. It is the standard switching device in 11 kV and 22 kV distribution substations.
        What do C, F and V mean in an RMU configuration such as CCF or CCV?
        C is a cable switch (load break switch for a ring cable), F is a fuse-switch combination for a transformer, and V is a vacuum circuit breaker feeder with a protection relay. A CCF RMU has two ring switches and one fused transformer feeder.
        What does LSC2 mean on MV switchgear?
        LSC2 is a loss of service continuity category from IEC 62271-200. It means that when one functional unit's accessible compartment is opened, the busbar and the other functional units can stay in service.
        What does IAC AFL 20 kA 1 s mean?
        It is the internal arc classification. A means accessibility restricted to authorised personnel, F, L and R are the front, lateral and rear sides tested, and 20 kA for 1 s is the arc current and duration the switchgear was type-tested for, while still protecting people standing at those sides.
        When should a transformer feeder use a circuit breaker instead of fuses?
        Fuse-switch combinations are common up to about 1000 to 1250 kVA at 11 kV. Larger transformers, or projects needing relay protection, discrimination with LV breakers, remote tripping or SCADA, usually use a vacuum circuit breaker with a protection relay. The utility's rules decide in the end.
        Is SF6 being phased out of RMUs?
        Yes in the EU. Regulation (EU) 2024/573 bans SF6 in new MV switchgear up to 24 kV from 2026 and up to 52 kV from 2030, with limited exceptions. Manufacturers now offer SF6-free RMUs using vacuum interruption with clean air, dry air or solid insulation, and many utilities outside the EU are trialling or adopting them.

        Standards referenced

        • IEC 62271-1 Common specifications
        • IEC 62271-200 Metal-enclosed switchgear above 1 kV up to 52 kV
        • IEC 62271-100 / -102 / -103 / -105 Breakers, earthing switches, switches, switch-fuses
        • IEC 62271-213 and IEC 61243-5 Voltage presence indication
        • IEC 60282-1 Current-limiting fuses
        • AS 62271.200, AS 2067 (Australia)
        • Regulation (EU) 2024/573 (fluorinated gases)

        Quick summary in your language

        Read this lab's key points in English, Urdu, Hindi or Arabic. The lab itself is in English.

        This lab lets you operate an 11 kV ring main unit in 3D, use the interlocks and size MV switchgear. Interlocks are there to stop unsafe operation, never bypass them.

        Project checks

        Verify each RMU functional unit against the required duty and approved single-line diagram. Check earthing and interlocking arrangements alongside the device ratings and cable entry details.

        NEXT STEP

        Where to go from here

        Related labs that pick up where this one ends.

        Medium Voltage hubAll 16 MV labs and the 788-question MV bank.MV HUBMV Cables & Accessories LabMV XLPE cable lab: 3D cable layers, IEC 60287 rating for 6.6 to 33 kV, voltage drop and short-circuit checks,…MV-502 · previousDistribution Transformer LabOil and cast resin transformers in 3D, animated Dyn11 vector groups, parallel operation, kVA sizing, losses,…MV-504 · nextHV Switchgear & Ring Main Unit LabSelect RMU ratings to IEC 62271, size HV fuses and relays, practise switching with live interlocks and…HV-503 · HV view
        Track what you have opened on My progress.All labs → · Ask the Copilot →