Switching, Safety & Permits Simulator

Choose a job, then build the switching program from the step cards in the right order. Press Run and watch it play out on a live 11 kV ring. Mistakes such as earthing a live cable or issuing a permit too early are caught and scored.

In short

  • A switching program lists every operation in order, who does it and where, and is checked before anyone touches the network.
  • The core sequence is isolate, prove dead, earth, lock and tag, then issue the permit. Never earth before proving dead.
  • Use the normally open point to back-feed customers before opening switches, so only the work area loses supply.
  • Every earth applied for the work is listed on the permit to work, and the permit is cancelled before any earth is removed.
  • Each utility has its own safety rules, authorisation levels and forms. This simulator teaches the common logic, not one utility's rulebook.

Switching Program Simulator 2D 4D replay

Step cards

Click a card to add it to your program. Some cards are traps.

Your program

    Control room log

      What is a switching program?

      A switching program (or switching schedule) is a written, numbered list of every operation needed to make equipment safe for work and to restore it afterwards. It names each switch, its location, the operation and the person doing it. It is prepared and checked in advance, then each step is carried out and confirmed with the control room. Following it exactly is what stops people being hurt by live equipment.

      The safe isolation sequence

      1. Plan the outage: notify affected customers and transfer load using the normally open point where possible.
      2. Isolate: open every switch that could make the equipment live, including LV back-feeds from generators or other transformers.
      3. Secure the isolation: lock the switches open and fit danger tags.
      4. Prove dead: test the voltage indicator, check the circuit is dead, and test the indicator again.
      5. Earth: apply earths at every point of isolation, so the work area is between earths.
      6. Lock and tag the earths, then issue the permit to work listing all isolation and earthing points.

      Restoration runs in reverse: the permit is cancelled, earths are removed, and then the equipment is re-energised.

      PractitionerClosing the normally open point parallels two feeders for a short time. Before closing it, check both feeders come from the same source busbar or are in phase, and that the loads and protection can take the ring being closed.

      Regional notes

      GCC

      Utilities run their own safety rules with authorised persons, control room permission for every operation, and their own permit forms. Contractors work under the utility's permits for utility-owned equipment.

      Australia

      Network operators follow their own safety rules based on national guidelines such as ENA NENS 04, with access authorities and recipient training.

      New Zealand

      The EEA Safety Manual: Electricity Industry (SM-EI) sets the common framework for switching, isolation and work permits.

      Asia

      Utilities such as TNB and SP Group apply their own safety rules and licensing for switching operators.

      Test yourself

      0 / 6

      6 questions. Pick an answer to see the explanation. Practise about 50 more MV-510 questions in the MV Question Bank.

      Frequently asked questions

      What is the correct order for MV isolation?
      Isolate from all sources, lock and tag the isolation points, prove dead with a tested indicator, apply earths at each point of isolation, lock and tag the earths, and then issue the permit to work.
      Why prove dead before earthing?
      An earth switch closed onto a live circuit creates a full short circuit at the switch. Even with a fault-making rated earth switch this trips the source, damages equipment and can injure the operator.
      Why close the normally open point first?
      Closing the NOP back-feeds the substations beyond the work area from the other end of the ring before the work section is opened, so those customers do not lose supply.
      When can earths be removed?
      Only after the permit to work has been cancelled and everyone has left the work area, following the restoration steps in the switching program.

      Standards referenced

      • EN 50110-1 Operation of electrical installations
      • IEC 61936-1 Power installations above 1 kV
      • ENA NENS 04 (Australia)
      • EEA SM-EI (New Zealand)
      NEXT STEP

      Where to go from here

      Related labs that pick up where this one ends.

      Medium Voltage hubAll 16 MV labs and the 788-question MV bank.MV HUBMV Testing & Commissioning LabVirtual MV commissioning tests: IR and PI, VLF withstand and tan delta to IEEE 400.2, transformer ratio and…MV-509 · previousUtility Approvals & Interface WorkflowPlan a new 11 kV utility connection from load application to energisation: documents per stage, a Gantt with…MV-511 · nextHV Safety & Switching Operations LabPractise HV switching programs, calculate arc flash energy and PPE, see approach boundaries in 3D, follow…HV-512 · HV view
      Track what you have opened on My progress.All labs → · Ask the Copilot →

      © 2026 Eng. Mannan Maqsood | Engineering Excellence Through Interactive Labs

      VERIFY ALL FIGURES AGAINST CURRENT MANUFACTURER DATASHEETS AND LOCAL AUTHORITY REQUIREMENTS BEFORE DESIGN SIGN-OFF.

      Share this pageFollow