How does a new building get an MV supply?
When a building's load is too large for an LV connection, the utility asks for a substation on the developer's land. The developer's consultant applies with the load estimate, the utility replies with its connection conditions (substation size, number of transformers, cable route, fees), and the consultant submits the substation design for approval. The developer builds the room to the utility's standard, the utility or an approved contractor installs the RMU, transformers and cables, and after tests and inspection the utility energises and meters the supply.
What usually causes delays?
- Incomplete or non-compliant submissions that come back with comments.
- Room not ready: wrong dimensions, missing louvres, doors, trench covers or earthing, or the area not cleared.
- Cable route problems: wayleaves, road crossings and other utilities' services.
- Long equipment lead times, especially for larger transformers.
- Late fees or connection agreements.
PractitionerGet the utility's room standard and the load application in early, ideally at concept design. Many delays come from the architecture freezing before the substation location, size and access are agreed.
Regional notes
GCC
Utilities such as DEWA, ADDC/AADC, SEWA, KAHRAMAA, SEC, MEW and EWA run online portals for load applications, design submissions and inspections. In many cases the utility supplies and installs the RMU and transformers, and the developer provides the room and pays connection charges. Civil defence approval of the substation room is also needed.
Australia
Connections follow the National Electricity Rules connection process and each distributor's requirements. In New South Wales, contestable works are designed and built by Accredited Service Providers (ASP Level 1, 2 and 3) and then handed over to the distributor.
New Zealand
Lines companies such as Vector and Orion run their own connection processes, with approved contractors for network extensions and an agreed point of supply.
Asia
Utilities such as TNB and SP Group publish supply application guides with staged submissions, substation requirements and timelines.