4D Substation Project Simulator

Run a full 11 kV substation project in one place. Each step feeds the next: load, transformers, RMU, cable, room and programme. You finish with a design summary, a bill of quantities with your own rates, and a 4D build of the substation you designed.

In short

  • The design chain runs load → transformers → RMU → MV cable → room → approvals and programme. A change early on ripples through everything after it.
  • Maximum demand, not connected load, sizes the transformers. Allow for diversity, growth and the planned loading in hot climates.
  • Above roughly 1000 to 1250 kVA, transformer feeders usually move from fuse-switches to circuit breakers with relays.
  • The substation room and utility approvals usually sit on the critical path to energisation.
  • Cost rates in this simulator are examples only. Replace them with current quotes or your own cost database before using the totals.

Project Simulator 3D 4D

Work through the six steps. Every change updates the design summary, the 3D model, the BOQ and the programme.

Rated with the IEC 60287 engine from MV-502, direct buried trefoil, using your region's soil defaults.

Week 0 ·

Bill of Quantities & Cost Estimate Editable

Quantities come from your design. The rates are example placeholders: type in your own. Totals update live.

Example rates only, converted at fixed indicative exchange rates.
ItemQtyUnitRateAmount
Total (excluding utility fees and VAT/GST)

Programme to Energisation Gantt

How does an MV substation project come together?

Every decision depends on the one before. The load estimate sets the number and size of transformers. Their size sets the RMU transformer feeders (fuse or breaker), the LV fault level and the LV board rating. The ring capacity the utility wants sets the MV cable size. The equipment sets the room size, ventilation and access, and the room and approvals usually set the date the building gets power. Running these together, instead of in separate silos, is what keeps a project on time.

PractitionerFreeze the substation location and room size early with the architect and the utility. Track long-lead items (transformers, RMUs, LV boards) from the first design stage, and get the utility's ring cable size and route before the civil design is fixed.

What goes into the cost?

  • Equipment: RMU, transformers, LV main board, MV and LV cables and terminations.
  • Civil and building works: room, trench, plinths, doors, louvres, fire rating.
  • Earthing, testing and commissioning.
  • Utility connection charges and fees, which are often a large share and set by the utility.

ExpertAdd the cost of losses (MV-504) to the transformer comparison. Over 25 years, the present value of losses for a large transformer can be similar to its purchase price, which often justifies a lower-loss unit.

Regional notes

GCC

Utilities often supply and install the RMU and transformers, so the developer's BOQ may cover only the room, LV board and connection charges. Check the utility's scope split.

Australia and New Zealand

Contestable works may be built by accredited contractors and handed over, so the developer's scope can include the MV equipment and cables.

Asia

Scope splits and charges vary by utility. Check whether the utility or the developer supplies the switchgear and transformers.

Test yourself

0 / 5

5 questions. Pick an answer to see the explanation. Practise about 50 more MV-516 questions in the MV Question Bank.

Frequently asked questions

How many transformers does a building need?
Divide the maximum demand (with growth) by the planned loading of each unit and round up to standard sizes, keeping each unit at or below the largest size the utility accepts. Add a spare (N+1) if the building needs supply during a transformer outage.
How is MV cable size chosen for a ring?
Utilities usually set the ring cable size from the capacity the ring must carry when fed from one end. Rate it for the real installation with IEC 60287 or the manufacturer's tables and check the short-circuit rating.
Are the cost rates in this simulator real?
No. They are example placeholders to show how the BOQ works. Replace them with current supplier quotes or your own cost database.
What usually sets the energisation date?
The utility approval, the substation room handover and long-lead equipment such as transformers. The programme section shows which of these is on the critical path for your inputs.

Standards referenced

  • IEC 60076 Power transformers
  • IEC 62271-200 MV switchgear
  • IEC 60287 and IEC 60502-2 MV cables
  • IEC 61936-1 Power installations above 1 kV
NEXT STEP

Where to go from here

Related labs that pick up where this one ends.

Medium Voltage hubAll 16 MV labs and the 788-question MV bank.MV HUBCondition Monitoring & Failure ForensicsRead DGA on an interactive Duval Triangle, classify thermography hot spots, read partial discharge trends and…MV-515 · previousHV Installation & Site Works LabCalculate cable pulling tension and sidewall pressure, plan trenches and transformer lifts, follow an 11 kV…HV-517 · HV viewLV Switchgear Design LabCarry the design downstream to the LV panels.E-127
Track what you have opened on My progress.All labs → · Ask the Copilot →

© 2026 Eng. Mannan Maqsood | Engineering Excellence Through Interactive Labs

VERIFY ALL FIGURES AGAINST CURRENT MANUFACTURER DATASHEETS AND LOCAL AUTHORITY REQUIREMENTS BEFORE DESIGN SIGN-OFF.

Share this pageFollow