MV-508 · Phase 2 Design & analysis

MV Earthing & Step/Touch Lab

Lay out an earth grid, add rods and a surface layer, and check mesh and step voltages against what a person can tolerate. Then watch the surface potential rise in 3D and walk through the substation during a fault.

In short

  • During an earth fault, current flows into the ground through the grid and raises its potential. That ground potential rise (GPR) is IG × Rg.
  • Touch voltage is between a hand on earthed metal and the feet 1 m away. Step voltage is between two feet 1 m apart. Both must stay below tolerable limits.
  • IEEE 80 tolerable touch voltage for a 50 kg person is (1000 + 1.5 Cs ρs) × 0.116 / √ts. A crushed rock layer raises it a lot.
  • Closer grid spacing lowers the mesh voltage, rods help in high-resistivity soil, and faster fault clearing raises the tolerable limits.
  • Australia and New Zealand mainly use the risk-based ENA EG-0 approach with AS 2067. IEEE 80 and EN 50522 are common elsewhere.

Earth Grid Designer (IEEE 80) Calc

Enter the site and fault data. Results update live, and the grid plan shows your layout.

Design result

Grid plan

Details

IEEE 80 equations for a rectangular grid with rods on the perimeter (Sverak resistance, Km/Ki mesh and Ks step factors). Use a full study with measured soil layers for final design.

3D Surface Potential Map 3D

Height and colour show the surface potential as a fraction of GPR during the fault. Dips between conductors drive the mesh (touch) voltage. The steep slope outside the grid drives the step voltage.

Drag: rotate · Wheel/pinch: zoom

Field from a uniform current leakage along the conductors and rods, with an image source, scaled so the grid sits at GPR. Illustrative for uniform soil.

4D Fault Walk-Through 3D 4D

A person walks from the middle of the substation out past the fence while an earth fault happens. The panel shows their step voltage live, and the touch voltage if they touch the fence or equipment.

What are step and touch voltages?

When earth fault current enters the soil through a substation earth grid, the ground surface around it rises in voltage, highest over the conductors and falling away with distance. A person touching earthed steel (which is at the full grid potential) while standing on ground at a lower potential experiences a touch voltage. A person walking across the gradient experiences a step voltage between their feet. The highest touch voltage inside a grid is usually in the middle of a corner mesh, called the mesh voltage.

How do you make an earth grid safe?

  • Lower the grid resistance: a bigger area, more conductor, rods into lower-resistivity layers.
  • Reduce the mesh size: closer conductor spacing flattens the surface potential.
  • Add a surface layer: crushed rock or asphalt adds resistance in series with the feet and raises the tolerable limits.
  • Clear faults faster: tolerable voltages rise with 1/√t.
  • Control the boundary: a grading ring outside the fence and bonding the fence correctly.
  • Cut the current into the grid: cable screens and overhead earth wires carry part of the fault current back to the source (the split factor).

ExpertSoil is rarely uniform. Wenner tests at several spacings usually show two or more layers. A low-resistivity bottom layer makes long rods very effective, while a high-resistivity top layer acts like a surface layer for step voltages but makes rods essential. Also check transferred potentials on LV neutrals, telecom cables and pipes leaving the site.

Distribution substations inside buildings

For building substations, the MV earth fault current is often limited by the neutral earthing resistor at the primary substation, and the building's foundation and structure form a large global earthing system. Many codes allow a combined HV and LV earth when the EPR stays below set limits, otherwise the HV and LV earths must be separated. Check the utility's earthing rules and the MV earth fault current and clearance time they give you.

Regional notes

GCC

IEEE 80 and BS EN 50522 are common references, with utility rules for earth pit construction, testing and the maximum earth resistance of distribution substations. Dry desert sand has very high resistivity near the surface, so deep rods or chemical earthing are often used.

Australia and New Zealand

AS 2067 with the ENA EG-0 risk-based method is used. EG-0 sets touch voltage limits based on the probability of contact and fault frequency, rather than one fixed value.

Asia

IEEE 80 is widely used, with national codes such as IS 3043 in India.

Test yourself

0 / 8

8 questions. Pick an answer to see the explanation. Practise about 50 more MV-508 questions in the MV Question Bank.

Frequently asked questions

What is ground potential rise (GPR)?
GPR is the voltage that the earth grid rises to, relative to remote earth, during an earth fault. It equals the current flowing into the grid times the grid resistance.
What is the difference between step and touch voltage?
Touch voltage is between a hand on an earthed object and the feet, normally taken 1 m away. Step voltage is between two feet 1 m apart. Touch voltage limits are much lower because the current path crosses the heart.
Why is crushed rock used in substations?
A high-resistivity surface layer (often 2,000 to 5,000 ohm-m when wet) adds resistance in series with the feet, which greatly raises the tolerable step and touch voltages.
What is the split factor in IEEE 80?
The fraction of the total earth fault current that actually flows into the substation grid. The rest returns through cable screens, overhead earth wires and other paths.

Standards referenced

  • IEEE 80 Substation grounding
  • EN 50522 Earthing above 1 kV AC
  • IEC 61936-1 Power installations above 1 kV
  • AS 2067 and ENA EG-0 (AU/NZ)
  • IS 3043 (India)

Quick summary in your language

Read this lab's key points in English, Urdu, Hindi or Arabic. The lab itself is in English.

This lab designs a substation earth grid to IEEE 80 and checks grid resistance, touch and step voltage in 3D. Measure the soil resistivity first, as it drives the whole design.

Project checks

Evaluate the earthing grid under the approved soil, current and clearing assumptions. Check where people can touch conductive parts or cross potential gradients, including transferred potentials beyond the grid.

NEXT STEP

Where to go from here

Related labs that pick up where this one ends.

Medium Voltage hubAll 16 MV labs and the 788-question MV bank.MV HUBMV Protection & Relay CoordinationPlot IEC IDMT relays, HV fuses and LV ACBs on one TCC chart, check grading margins, inrush and damage curves,…MV-507 · previousMV Testing & Commissioning LabVirtual MV commissioning tests: IR and PI, VLF withstand and tan delta to IEEE 400.2, transformer ratio and…MV-509 · nextHV Substation Earthing LabDesign an IEEE 80 earth grid, calculate GPR, touch and step voltages, see the surface potential in 3D, run a…HV-508 · HV view
Track what you have opened on My progress.All labs → · Ask the Copilot →